Vektek, Inc. thinks machine hours is the best activity base for its manufacturing overhead. The estimate of annual overhead costs for its jobs was $2,050,000

Vektek, Inc. thinks machine hours is the best activity base for its manufacturing overhead. The estimate of annual overhead costs for its jobs was $2,050,000. The company used 1,000 hours of processing on Job No. B12 during the period and incurred overhead costs totaling $2,100,000. The budgeted machine hours for the year totaled 20,000. How much overhead should be applied to Job No. B12?

Entry field with correct answer
$2,050


$2,100


$105,000


$102,500


Norman Company manufactures customized desks. The following pertains to Job No. 953:

Direct materials used
$22,800
Direct labor hours worked
600
Direct labor rate per hour
$16.00
Machine hours used
400
Applied factory overhead rate per machine hour
$30.00

What is the total manufacturing cost for Job No. 953?

Entry field with correct answer
$44,400


$47,200


$50,400


$41,200