In January, Dieker Company requisitions raw
materials for production as follows: Job 1 $900, Job 2 $1,200, Job 3 $700, and
general factory use $600. During January, time tickets show that the factory
labor of $6,000 was used as follows: Job 1 $2,200, Job 2 $1,600, Job 3
$1,400, and general factory use $800.
Prepare the job cost sheets for each of the three jobs.
Prepare the job cost sheets for each of the three jobs.
Job 1
|
||||
Date
|
|
Direct Materials
|
|
Direct Labor
|
1/31
|
|
|
|
|
Job 2
|
||||
Date
|
|
Direct Materials
|
|
Direct Labor
|
1/31
|
|
|
|
|
Job 3
|
||||
Date
|
|
Direct Materials
|
|
Direct Labor
|
1/31
|
|
|
|
|
Sam Bowden believes actual manufacturing overhead
should be charged to jobs. Do you agree?